Vår Energi progressing more than 25 early phase projects offshore Norway

Feb. 11, 2025
Production from the extensive Balder X redevelopment project should begin by mid-2025.

Barents Sea project updates

To the north in the Barents Sea, Vår Energi is a partner in the Equinor-operated Johan Castberg development, which should go onstream in the current quarter. Drilling is progressing as planned, with 14 of the 30 development wells completed; these should be sufficient to attain plateau production of 220,000 boe/d.

Infill drilling and further development phases should follow to extend the plateau, along with a new round of exploration drilling in the area over the next few years.

Following a successful appraisal well last year on the Countach oil discovery, close to the Goliat field in the Barents Sea, Vår Energi plans to follow up with two or three further wells on the Goliat ridge this year, pursuing potential recoverable resources of more than 100 MMboe.

Norwegian Sea project updates

At Halten East in the Norwegian Sea, also operated by Equinor, the subsea tieback project is on track to start up by the end of March, with the first completed wells delivering better than expected results.

Halten East contains about 100 MMboe of confirmed recoverable gas and condensate, which will be exported through the existing Åsgard area infrastructure, with unrisked potential for a further 100 MMboe to 200 MMboe in the area under review for future development. 

Vår Energi in the news:

Courtesy SLB OneSubsea
SLB OneSubsea signs agreement with Vår Energi for upcoming subsea developments in Norway
Subsea

Vår Energi, OneSubsea collaborate to speed up tiebacks offshore Norway

Feb. 4, 2025
OneSubsea has signed a letter of intent to supply subsea production systems for Vår Energi’s projects on the Norwegian Continental Shelf.
Courtesy Aker Solutions
Ringhorne June 2024
North Sea & Europe

Vår Energi enters offshore Norway maintenance and modification partnership

Jan. 22, 2025
Vår Energi has formed a strategic partnership with Aker Solutions, Honeywell and StS-ISONOR.
Courtesy COSL
cosl prospector
North Sea & Europe

Offshore Elgol gas find may not be economic to develop

Jan. 17, 2025
Vår Energi has discovered gas in the Elgol prospect in the Barents Sea, but the find may be sub-commercial, according to the Norwegian Offshore Directorate.
Courtesy Vår Energi
Aker Solutions secures new frame agreement with Vår Energi
North Sea & Europe

Aker Solutions signs long-term North Sea maintenance deal with Vår Energi

Dec. 26, 2024
Vår Energi has awarded Aker Solutions a five-year maintenance and modifications service contract for the Jotun, Balder and Ringhorne field production facilities.
Courtesy INPEX
EXL007 Trudvang CCS Project map
North Sea & Europe

Change of ownership for North Sea Trudvang CCS storage license

Dec. 16, 2024
Vår Energi CCS has assumed operatorship of the Trudvang CO2 storage license in the northern Norwegian North Sea, east of the Sleipner field.
Courtesy Vår Energi
Barents Sea Countach oil well confirms prospectivity of Goliat ridge
Drilling & Completion

Barents Sea Countach oil well confirms prospectivity of Goliat ridge

Dec. 13, 2024
Vår Energi has proven oil with an appraisal well on the 2023 Countach discovery.
Courtesy Lars Morken/Equinor
Johan Castberg FPSO
Production

Barents Sea Johan Castberg startup delayed to early 2025

Dec. 12, 2024
Equinor has pushed back the estimated first oil date for the Johan Castberg FPSO in the Barents Sea to January-February 2025.
Courtesy Aker BP
Alvheim FPSO
North Sea & Europe

Concedo joins Aker BP in North Sea Bøyla field

Nov. 12, 2024
Vår Energi ASA has concluded the sale of its 20% interest in the Bøyla field in the Norwegian North Sea to Concedo for $24 million (post-tax).
Courtesy DeepOcean
Vår Energi enlists DeepOcean for 2025 subsea scope
Subsea

DeepOcean providing subsea IMR for Vår Energi Norway fields

Oct. 30, 2024
Vår Energi has booked DeepOcean for an inspection, maintenance and repair (IMR) campaign next year offshore Norway.
Courtesy Vår Energi
Jotun FPSO
Production

North Sea Balder X startup delayed, two more development phases planned

Aug. 22, 2024
Vår Energi has pushed back the targeted startup date for its Balder X development in the Norwegian North Sea to second-quarter 2025.
About the Author

Jeremy Beckman | Editor, Europe

Jeremy Beckman has been Editor Europe, Offshore since 1992. Prior to joining Offshore he was a freelance journalist for eight years, working for a variety of electronics, computing and scientific journals in the UK. He regularly writes news columns on trends and events both in the NW Europe offshore region and globally. He also writes features on developments and technology in exploration and production.