Toreador aims for first gas production from Turkey's South Akcakoca sub-basin
Offshore staff
(Middle East) - Toreador Resources Corp. says that 2006 development plans and budgets for the South Akcakoca sub-basin natural gas project, located offshore Turkey in the Black Sea, were unanimously approved by the project's joint operating committee in a meeting in Ankara, Turkey.
Toreado aims to achieve first gas production from the project by the second half of 2006.
The approving committee consists of representatives of the project's partners, TPAO (the Turkish national oil company), Toreador (operator in the South Akcakoca sub-basin) and Stratic Energy Corp.
The development plans include drilling at least six development wells during the next six months on the Akkaya and Ayazli structures.
In addition, the partners agreed to drill two wells and have the option to drill a third well in the deeper waters of the project area on the Akcakoca structure during 2006.
Funding for Toreador's share of project costs will be drawn from a portion of the proceeds of its recent issues of equity and convertible notes, which resulted in net proceeds in excess of $100 million. Remaining funds will be used for the company's other exploration and development programs through 2006.
To facilitate production of first gas by the second half of 2006, the committee approved the contracting of a second jackup rig for a minimum of six months.
TheSaturnwill be used in conjunction with its sister rig, the Prometheus, to complete further exploration, appraisal and development drilling, as well as installation of production platforms in the shallow waters of the South Akcakoca sub-basin.
TheSaturn is expected to arrive in late December, and the Prometheus is currently drilling the Ayazli-2A development well.
In addition, the committee approved the contracting of Atwood Oceanic's semi-submersible rig Southern Cross to drill the planned exploration and appraisal wells in the deeper waters of the South Akcakoca sub-basin. It is anticipated that the Southern Cross will be available by April 2006.
Development of the project's offshore pipeline system, onshore gas processing facilities, and the onshore tie-in to the national gas grid has already begun. The approximately 17-km pipeline from the site of the processing facilities to the national grid is currently under construction.
The contract for the construction of offshore production platforms is expected to be awarded by the end of 2005.
In acreage to the east of the South Akcakoca sub-basin, the partners have agreed to drill up to three exploration wells on prospects similar to the current discoveries.
As per the original joint venture agreement, TPAO will be the operator in the permit area outside of the South Akcakoca sub-basin.
Currently, a high-definition 2D seismic survey is underway over the area in order to identify potential drilling locations with the exploration drilling program planned to begin in the second half of 2006.
Toreador President and CEO, G. Thomas Graves III, says,"Although the Black Sea area in Turkey is a new frontier for offshore exploration, the productive and collaborative efforts of the partners have moved this project at a rapid and successful pace. To put the pace of development in context, since completing the discovery well at the end of September 2004, we have drilled an additional five development and appraisal wells, completed 2D and 3D seismic programs that will drive further development, and have begun construction of the onshore and offshore production infrastructure.
"In addition to the development of the 50,000 acres in the South Akcakoca sub-basin, the partners are also committed to further exploration in the remaining 912,000 acres of the Western Black Sea permi, and are proceeding with planning for future activities."
11/29/05