Two more SBM FPSOs nearing completion

May 9, 2024
SBM Offshore provides various FPSO updates in its latest trading report.

Offshore staff

MONACO — SBM Offshore expects to deliver the FPSO Almirante Tamandaré to Petrobras later this year, the company said in a trading update.

The topside modules lifting campaign has finished, and integration and commissioning activities are progressing. The completed platform should produce first oil from the Búzios Field in the Santos Basin offshore Brazil next year.

As for other FPSOs under construction, topside modules lifting is nearing completion for the Alexandre de Gusmão for the Mero Field in the Santos Basin—again, first oil is expected in 2025. Topside fabrication is advancing for the FPSO ONE GUYANA, which is due to deliver first oil next year from the Yellowtail Field.

Engineering and procurement has started for the FPSO Jaguar for the Whiptail development.

Later this year, SBM Offshore and Technip Energies expect to officially launch their new joint venture EkWiL as a floating offshore wind specialist proposing a wide range of solutions. It will bring together the two companies’ engineering and delivery capabilities and complementary technologies to create integrated floating solutions. Goals include enhanced execution certainty and cost competitiveness for floating offshore wind projects.