IOG restores North Sea Saturn Banks gas production

Nov. 28, 2022
IOG has restarted production from the Blythe and Elgood field wells in the UK southern North Sea following shutdown works.

Offshore staff

LONDON — IOG has restarted production from the Blythe and Elgood field wells in the UK southern North Sea following shutdown works.

Both wells are now exporting gas through the subsea Saturn Banks pipeline system, which underwent repressurization following final connection, dewatering and backgassing of the system’s outer section to the Southwark field wells.

In parallel, additional modifications have finished at the Saturn Banks Reception Facilities onshore at the Bacton terminal in Norfolk, to de-risk the potential for future shutdowns.

At the Southwark A2 well, hydraulic stimulation operations should continue into December. The well should deliver first gas by year-end. A1 will then be completed.

11.28.2022