SINGAPORE – Three sets of topsides have departed the Sembcorp Marine Admiralty Yard for the TotalEnergies-operated Tyra field in the Danish North Sea.
The two wellhead topsides, one riser topside, and two bridges are loaded onboard the heavy transport vessel BigRoll Beaufort.
According to Noreco, a partner in the Tyra field redevelopment, the voyage should last around one month, with installation expected to follow during late August-early September.
In December 2019, Sembcorp Marine won a contract to construct six topside modules and four bridges for the project. The remaining topside modules and bridges should be delivered in January 2022.
07/26/2021