Three sets of topsides have departed the Sembcorp Marine Admiralty Yard for the Tyra field in the Danish North Sea.
(Courtesy Sembcorp Marine)
Topsides and bridges for the Tyra redevelopment project.
Offshore staff
SINGAPORE – Three sets of topsides have departed the Sembcorp Marine Admiralty Yard for the TotalEnergies-operated Tyra field in the Danish North Sea.
The two wellhead topsides, one riser topside, and two bridges are loaded onboard the heavy transport vessel BigRoll Beaufort.
According to Noreco, a partner in the Tyra field redevelopment, the voyage should last around one month, with installation expected to follow during late August-early September.
In December 2019, Sembcorp Marine won a contract to construct six topside modules and four bridges for the project. The remaining topside modules and bridges should be delivered in January 2022.