Subsea structures in place at Karish offshore Israel

June 22, 2020
TechnipFMC and Allseas have completed two major components of Energean’s Karish gas project in the Mediterranean Sea, offshore Israel.

Offshore staff

LONDONTechnipFMC and Allseas have completed two major components of Energean’s Karish gas project in the Mediterranean Sea, offshore Israel.

Allseas’ Solitaire completed installation of the 90.3-km (56-mi), 30-in. and 24.in gas sales pipeline in water depths of up to 1,700 m (5,577 ft).

The full program included placement of a tie-in manifold structure in 72 m (236 ft) water depth.

On average, excluding the beach pull, the rate of laying was 4,578 m/d (15,019 ft/d).

TechnipFMC’s construction support vessel Normand Cutter installed the production manifold, subsea isolation valve foundations and structures.

During 4Q, installation should get under way of the three sets of risers - 2 x10-in. and 1 x 16-in. - that will connect the three producing wells to the FPSO and then to the gas sales pipeline, finishing in 1Q 2021.

Currently the Karish development is around 80% complete, Energean said.