Offshore staff
OSLO, Norway – Fred. Olsen Windcarrier’s Blue Tern has completed turbine installation at the Trianel Windpark Borkum II (TWB II), 45 km (28 mi) offshore the northern coast of Borkum Island, Germany.
In February, the company was contracted to install the remaining 11 Senvion 6.2M152 turbines on TWB II (out of a total of 32). Related company, Global Wind Service, was already on the project delivering technicians, QA and site management for the installation and mechanical completion of all 32 turbines.
The total wind farm capacity will be 200 MW when finished.
Companies involved in the project are EWE AG with a share of 37.5% and a joint venture of the power utility of the city of Zurich with 24.51%. The municipal utilities cooperation Trianel, along with 17 municipal utilities from Germany, holds a share of 37.99%.
05/18/2020