A/S Norske Shell has contracted Kvaerner for the disposal and demolition of the subsea compression pilot at Nyhamna.
Offshore staff
LYSAKER, Norway– A/S Norske Shell has contracted Kvaerner for the disposal and demolition of the subsea compression pilot at Nyhamna.
The scope of work consists of removal and demolition of about 2,200 metric tons of modules. The modules will be transported from Nyhamna to Kvaerner’s facilities at Stord for dismantling and recycling.
The work will start immediately and the first part, consisting of removal of modules from the test pit will be completed in 2017. The remaining modules will be removed in 2018.