Perenco concludes North Sea Gawain P&A

March 12, 2024
Perenco UK has completed P&A of three subsea wells at the Gawain gas field in the UK southern North Sea, along with the removal of associated subsea infrastructure.

Offshore staff

LONDON — Perenco UK has completed P&A of three subsea wells at the Gawain gas field in the UK southern North Sea, along with the removal of associated subsea infrastructure.

During the 160-day campaign, the company collaborated with various specialist contractors, using a jackup vessel with an air-based diving and ROV spread to allow for rig-based diving.

The program included more than 340 air dives. The focus now switches to post-decommissioning surveys to ensure the seabed area is clear and clean.

03.12.2024