The Q10 gas field is 20 km (12.4 mi) offshore in shallow water. The new facility, to be installed later this year in 21 m (69 ft) water depth, will be tied back to the existing P15d platform.
Koos-Jan van Brouwershaven, HFG’s CEO, said: “We will perform the full platform FEED and EPCI in one continuous program, rather than the traditional multi-stage approach.
“This enables a fasttrack delivery program, resulting in lower execution risk.”
The Q10-A topsides will weigh around 500 metric tons (551 tons) and the jacket 600 metric tons (661 tons).