Seatrium to perform EPC work for bp's Kaskida FPU

Dec. 26, 2024
Seatrium has signed a contract with bp to perform engineering, procurement, construction and onshore commissioning (EPC) work for the Kaskida floating production unit (FPU) project in the US Gulf of Mexico.

Seatrium has signed a contract with bp Exploration and Production to perform engineering, procurement, construction and onshore commissioning (EPC) work for the Kaskida floating production unit (FPU) project in the US Gulf of Mexico.  

The Kaskida greenfield development, for which bp took FID in July. is located about 250 miles southwest of New Orleans, Louisiana, in the Keathley Canyon area. 

Comprising a single topside module supported by a four-column semisubmersible hull, the Kaskida FPU is supported by subsea production wells in a water depth of about 6,000 ft. 

The Kaskida FPU has a capacity to produce 80,000 bbl/d of crude oil from six wells in the first phase of development.

The topsides for Kaskida will be integrated and lifted to the hull using Seatrium’s Goliath twin cranes with a combined lifting capacity of 30,000 tonnes. 

Recent Kaskida updates

Courtesy SLB OneSubsea
SLB OneSubsea awarded subsea boosting contract for Kaskida
US & Gulf of Mexico

SLB OneSubsea awarded subsea boosting contract for Kaskida

Oct. 30, 2024
Subsea boosting system to accelerate development of bp’s deepwater Gulf of Mexico project.
Courtesy Exmar Offshore/bp
kaskida rendering
Equipment Engineering

TechnipFMC secures contract for bp's Kaskida development in the Gulf of Mexico

Oct. 7, 2024
TechnipFMC has been awarded an integrated engineering, procurement, construction and installation contract by bp for its greenfield Kaskida development.
Courtesy Shell
Shell Green Canyon block 19 pipeline hub platform
US & Gulf of Mexico

Shell issues FID for new Gulf of Mexico crude oil pipeline

Oct. 6, 2024
Rome pipeline will move oil from bp’s Kaskida project starting at Green Canyon block 19.
Courtesy CNW Group/Enbridge Inc.
Enbridge Gulf of Mexico pipeline network
US & Gulf of Mexico

Enbridge sanctions new offshore pipelines to support bp's Kaskida development

Oct. 4, 2024
The $700-million project calls for new oil export and gas gathering lines in the deepwater Gulf of Mexico.
ID 324709788 © Cherezoff | Dreamstime.com
Digital rig and platform
Company News

bp selects ABS for class and service support for Kaskida project

Sept. 11, 2024
ABS will provide classification, engineering verification services for new FPU, subsea equipment.
Courtesy Audubon Engineering Company
Kaskida topsides
US & Gulf of Mexico

bp lets engineering contracts for Kaskida topsides, hull

Aug. 20, 2024
Exmar, Audubon chosen to undertake work for deepwater Gulf of Mexico platform.
Courtesy EXMAR Offshore
kaskida rendering
US & Gulf of Mexico

bp takes FID on GoM Kaskida project

July 30, 2024
Kaskida will be bp’s sixth hub in the GoM, featuring a new floating production platform with the capacity to produce 80,000 bbl/d of crude oil from six wells in Phase 1.
Courtesy bp
Production

Seatrium gets LoI for bp’s Kaskida FPU

June 5, 2024
BP Exploration & Production has awarded a letter of intent (LoI) to Seatrium concerning early engineering works for the Kaskida FPU in the US Gulf of Mexico.