PERTH, Australia — Woodside Energy has initiated FEED for Lambert West, a one-well tieback to the Angel platform offshore Western Australia to sustain LNG production from the North West Shelf project.
In the same region, upstream pipeline manufacturing for Woodside’s Scarborough gas field development is 86% complete, subsea structure manufacture has started and trunkline shore crossing preparations are underway close to the Pluto LNG reception area.
To the south, P&A continues at the Enfield Field center with nine of the 18 wells plugged and 13 of the 18 xmas trees removed. The FPSO Ngujima-Yin is in drydock in Singapore for a five-yearly maintenance turnaround but should return to production during the third quarter.
In the US Gulf of Mexico, SN101 well completion operations have started for the Shenzi North project.
As for Woodside’s Sangomar Phase 1 field development offshore Senegal, the 101-km network of rigid flowlines have been installed and tested, installation of the umbilical is progressing and 10 of the 23 development wells have been completed.
In Singapore, the Léopold Sédar Senghor FPSO topsides are undergoing integration and pre-commissioning works. Overall, the project is now more than 82% complete with first oil targeted in late 2023.