Semco Maritime awarded service role for North Sea Butendiek wind farm
Nov. 16, 2023
Semco Maritime has secured a balance-of-plant, operations and maintenance service contract for the Butendiek wind farm in the North Sea.
Offshore staff
ESBJERG, Denmark — Semco Maritime has secured a balance-of-plant, operations and maintenance service contract for the Butendiek wind farm in the North Sea, 32 km from the Island of Sylt near the German-Danish maritime median line.
The wind farm, operational since 2015, generates 288 MW through 80 Siemens 3.6-MW wind turbines.
Semco Maritime will enter the 10-year agreement from Jan. 1, 2024, with Siemens Gamesa holding the contract and full turbine maintenance and offshore logistics responsibility toward owner OWP Butendiek GmbH & Co. KG.
The balance-of-plant service work streams will include scheduled and unscheduled maintenance and inspections above water on the offshore substation and its foundation, and on the 80 wind turbine generator foundations.
Project operations will mainly take place from Havneby on the Danish Island Rømø.