Boskalis booked for Baltica 2 offshore wind cable installations

Sept. 6, 2023
PGE Polska Grupa Energetyczna and Ørsted have awarded Boskalis two contracts for the transportation and installation of export and array cables for the Baltica 2 wind farm offshore Poland.

Offshore staff

PAPENDRECHT, the Netherlands  PGE Polska Grupa Energetyczna and Ørsted have awarded Boskalis two contracts for the transportation and installation (T&I) of export and array cables for the Baltica 2 wind farm offshore Poland.

The work scope covers 107 array cables with a total length of more than 150 km and four 275-kV export cables with a combined length of close to 300 km.

In addition, Boskalis will perform seabed preparation works including leveling of the seabed, pre-trenching and removal of boulders. Once cable installation activities have finished, the company will place rock to protect and stabilize the cable protection systems.

Preparatory should start in 2025 with T&I activities to follow in 2027.

Boskalis will deploy two cable-laying vessels, a construction support vessel, a subsea rock installation vessel and a trailing suction hopper dredger. The cables will be installed in a pre-cut trench using the Megalodon plough deployed from Boskalis’ construction support vessel Falcon.

Baltica 2, with a planned capacity of up to 1.5 GW, is about 40 km offshore Leba and Ustka in the Baltic Sea.

09.06.2023