Offshore staff
Seaway 7 ASA, part of Subsea 7 S.A. Group, has been selected by Seagreen 1 Ltd. as a preferred supplier for the Seagreen 1A offshore wind project offshore Scotland.
Seagreen 1A lies adjacent to the existing Seagreen project that Seaway 7 is progressing, and it represents approximately 500 MW of additional renewable energy generation capacity.
Seaway 7’s scope of work is under final negotiation and may include the full engineering, fabrication, transport and installation of 36 foundations, transportation and installation of the offshore substation, and the procurement and installation of inner-array cables. Execution of the scope will be led from Seaway 7’s Aberdeen office.
The project is expected to commence in 2023 with offshore work beginning in late 2024 and could be operational by 2025 or 2026.
The timeframe and Seaway 7’s selection are subject to the Seagreen 1A project securing consent and a final investment decision by SSE Renewables and TotalEnergies.
The value related to this contract agreement, which is between $500 million and $750 million, is expected to be recognized in Seaway 7’s backlog after final contractual terms have been agreed.
Subsea 7 began its long-term collaboration with SSE Renewables in 2009 with the pioneering Greater Gabbard development and continued with Beatrice, Seagreen and Dogger Bank.
06.07.2022