ZWIJNDRECHT, Belgium – The joint venture ENGIE Solutions-Iemants has contracted DEME Offshore to transport and install the jackets and topsides for two Hollandse Kust offshore substations in the Dutch North Sea.
The company will also supply and install scour protection for both substations, which will be installed at the Hollandse Kust (noord) and (west Alpha) wind farms.
Installation of the scour protection and jacket for Hollandse Kust (noord) is planned for the second half of 2021, while the topsides for Hollandse Kust (noord) and jacket for (west Alpha) will be installed during the summer of 2022. The topsides for Hollandse Kust (west Alpha) is expected to be installed in 2023.