CNOOC has started production from the Dongfang 29-1 gas field development in the Yinggehai Basin offshore southern China.

CNOOC has started production from the Dongfang 29-1 gas field development in the Yinggehai Basin offshore southern China.

The location is in 68 m in the northwestern region of the South China Sea, between Hainan Island and northern Vietnam. Production facilities include a new unmanned wellhead platform and a submarine pipeline, with six development wells to be commissioned.

CNOOC expects to achieve peak production of 38 MMcf/d later this year.

The platform’s equipment layout has been optimized to make best use of available space, reducing overall investment costs, the company added.