BlueNord, a partner in the Tyra redevelopment project in the Danish North Sea, has issued an update based on an announcement by operator TotalEnergies.
The restart of the Tyra Field complex is on track, with rampup to the 8.1-MMcm/d technical capacity expected to take four months from the restart of production. That includes re-pressurization and activation of the connecting gas infrastructure.
First gas should flow around the end of March, although the restart could be earlier, depending on the current program’s progress.