Husky details offshore start-ups and shutdowns in 2020

Dec. 3, 2019
Husky Energy expects to achieve first production from the Liuhua 29-1 field offshore China by the end of next year, the company revealed in its 2020 capex forecast.

Offshore staff

CALGARY, CanadaHusky Energy expects to achieve first production from the Liuhua 29-1 field offshore China by the end of next year, the company revealed in its 2020 capex forecast.

The partners are targeting production of 45 MMcf/d of gas and 1,800 b/d of liquids.

Husky added that the West White Rose project offshore Newfoundland is around 55% complete with first oil planned around the end of 2022.

Next year the company anticipates maintenance shutdowns of two weeks at the Liwan gas project during 2Q; four weeks in total at the BD project offshore Indonesia; three weeks in 3Q at the SeaRose FPSO; and six to seven months off station at the Terra Nova FPSO (both off Newfoundland).

Another Canadian oil company, Suncor Energy, will allocate $1.1 billion next year to previously sanctioned E&P step-out developments, including the Terra Nova asset life extension.

12/03/2019

Courtesy SBM Offshore LinkedIn
FPSO Alexandre de Gusmão
Courtesy Shana News Agency; "South Pars Phase 11 Gas Production Rising" article published Nov. 10, 2024
South Pars Phase 11 Gas Production Rising
Courtesy Bruno Castro / Petrobras News Agency
Boaventura Energy Complex