Offshore staff
ZUG, Switzerland – Nord Stream AG has completed the gas-in procedure for the second string of the Nord Stream 2 pipeline through the Baltic Sea.
In line with design requirements, the string is filled with around 177 MMcm of technical gas, with a pressure of 103 bar (1,494 psi) in the pipeline, sufficient to start gas deliveries in the future.
The German authorities, however, have still not issued sign-off for start-up.
01/04/2022