Offshore staff
HOUSTON– McDermott International Inc. has successfully concluded the transportation and installation of a yoke-type single point mooring tower and hook up to an FSO vessel for PT Rekayasa Industri at the Banyu Urip field offshore Indonesia.Â
PT Rekayasa Industri was appointed by Mobil Cepu Ltd., an ExxonMobil subsidiary, as one of the engineering, procurement, construction, and installation contractors for the field.
McDermott Derrick Barge 30 carried out the installation and hook up.
The Banyu Urip full field development is planned to produce 165,000 b/d from facilities that include 48 wells on three well pads, a central processing facility, and a 60-mi (97-km) pipeline to transfer the processed oil to a 1.7 MMbbl FSO unit in the Java Sea.
12/02/2014