STAVANGER, Norway – Statoil and its partners Eni and Petoro have deferred final concept selection for the Johan Castberg project in the Barents Sea until summer 2015.
This takes in the Statoil-operated discoveries Skrugard and Havis discoveries, estimated to contain a total of 400-600 MMbbl of oil. This yearStatoil drilled exploration wells on other structures in the area to prove more oil for the development, but results fell below expectations.
“In total, we have not proven enough resources in Castberg to make the field viable for supporting infrastructure, including a pipeline to shore and an onshore terminal on its own,” said Arne Sigve Nylund, Statoil executive vice president for Development and Production Norway.
The partners are also unclear as to the level of support the Norwegian government might provide for establishing brand new infrastructure so far north.
They will now focus on three main issues:
06/30/2014