More platforms heading to South Pars Phase 13 offshore Iran
Nov. 25, 2019
The two remaining platforms for the Phase 13 development of the South Pars gas field in the Persian Gulf (platforms B and D) will be installed in the next four months, according to news service Shana.
Offshore staff
TEHRAN, Iran – The two remaining platforms for the Phase 13 development of the South Pars gas field in the Persian Gulf (platforms B and D) will be installed in the next four months, according to news service Shana.
Platform C is currently operational while Platform A is expected to start service next spring.
In 2015, development was set back when one of the platforms was damaged after being struck by a Singaporean vessel.