Legal insight informs risk allocation in FPSO construction contracts-full

Nov. 13, 2014
FPSO construction is inherently challenging. Such projects require the integration of distinct components: the hull, topsides and modules, plus the subsea mooring and riser systems, which require hook-up to subsea equipment, and commissioning of the vessel in the field. The unique design requirements of the business, the incorporation of new and old equipment, the integration of owner-provided equipment, and the use of multiple contractors provide the ingredients for potential delay.

Clear, concise extension time clauses help avoid problems

Baldev Bhinder
Ashurst LLP

FPSO construction is inherently challenging. Such projects require the integration of distinct components: the hull, topsides and modules, plus the subsea mooring and riser systems, which require hook-up to subsea equipment, and commissioning of the vessel in the field.

The unique design requirements of the business, the incorporation of new and old equipment, the integration of owner provided equipment, and the use of multiple contractors provide the ingredients for potential delay problems. The interdependent nature of various aspects of FPSO construction means that risk allocation of delay events, in particular, the extension of time and liquidated damages regime, needs to be carefully understood, assessed, and applied.

A typical construction contract delineates various delay events according to the risk assumed by the respective parties:

  • Owner's risk events, such as requests for additional works, are typically termed "Relevant Event(s)" with a corresponding right for a contractor to seek, among other things, an extension of time to the completion date on account of the Relevant Event
  • Neutral events such as those arising from inclement weather (or other force majeure events) are typically termed "Permissible Delay" and also will provide the contractor with a right for an extension of time
  • Contractor's risk events, such as labor shortages, are naturally at the risk of the contractor and will not entitle the contractor to an extension of time, thereby exposing it to liquidated damages for any delay beyond the completion date.

Extension of time clauses

Risk allocation for delay events must start with a proper understanding of extension of time (EOT) clauses. The common perception of EOT clauses is that it is intended to benefit the contractor because it extends the date for completion of the works for delay events, thereby reducing the period from which an owner can seek liquidated damages. Owners, therefore, typically view such clauses with considerable suspicion, and seek to limit its scope and application, with the belief that the fewer opportunities a contractor has to rely on an EOT clause, the greater the owner's chances to claim more liquidated damages. Such a belief is misplaced.

The reality is that EOT clauses operate for the benefit of the owner as well, as such clauses avoid the operation of what is known as the "prevention principle." The prevention principle is not a novel concept, having been established as far back as 1893. In essence, the prevention principle operates to preclude an owner from claiming any liquidated damages if some of the delay is due to its own, employees', or agents' default. In practical terms, this means that when the principle applies, time for completion of the works is set "at large." The contractor is no longer obliged to complete the works by the completion date but instead has to do so within a reasonable time. Flowing from that, the owner can no longer seek to claim liquidated damages from the contractor but, to the extent that the contractor has exceeded a reasonable time to complete the works, the owner has to prove its losses as general damages.

The practical ramifications of this principle can be startling.

Actions by the owner which are perfectly legitimate under a construction contract may still be characterized as prevention if those actions caused delay beyond the contractual completion date. Even when an owner's delay can be easily quantified, for example, late provision of a site to start work, the courts, under English law will not apportion liability for delay. This results in the position that even if the contractor would have been unable to complete on time, in the absence of a delay by the owner, the liquidated damages clause will still cease to apply if the owner is responsible for some of the delay.

Parties can seek to contract out of or modify the application of the prevention principle through the use of EOT clauses, for example, by providing an extension of time mechanism on account of such acts of the owner, that might otherwise amount to acts of prevention. Viewed from such context, an EOT clause takes on a different complexion – it is actually beneficial to the owner in that it preserves the right to liquidated damages in the event of delay attributable to the owner.

This is all the more so in the context of FPSO constructions, where there is a constant interface between the owner and contractor, whether in terms of coordination of the various components, integration of owner provided equipment, involvement of third party contractors employed directly by the owners, and the likelihood of variations that inevitably arise with building a customized piece of equipment for offshore operation. Extension of time clauses have no pro-forma standard in the FPSO market; hence, careful consideration should be given to prevention issues when allocating risks in such projects.

Risk allocation

A few key issues regarding risk allocation are described below.

Notification requirements in EOT clauses. Most extension of time clauses provide for a timeframe from which a contractor is to apply for an extension of time. Whether any timeframe stipulated for the notification of an extension of time should operate as a condition precedent to the operation of the clause depends on the wording of the EOT clause. Can a contractor who fails to notify the owner of a Relevant Event or does not do so within the stipulated time, then assert that it has been prevented by the acts of the owner, resulting in the disabling of the liquidated damages sanction?

The weight of the authorities seem to suggest it would inequitable to allow a contractor to be "better off by deliberately failing to comply with a notice condition than by complying with it" and that the contractor should not be able to "rely upon preventing conduct of the other party where it failed to exercise a contractual right which would have negated the effect of that preventing conduct."

The inherent conflicting interests of the owner and contractor in concurrent delay situations are illustrated in this diagram. (Courtesy Ashurst LLP)

Relevant Event occurring after completion date. When a contractor is in "culpable delay," i.e., it has missed the completion date due to its own fault, it is not uncommon for it to allege an act of prevention (e.g., additional works ordered by the owner), even though such acts of prevention have occurred after the completion date. Contractors may allege that the EOT mechanism does not apply to post completion events and it is therefore prevented from completing the work. If an act of prevention has occurred, post-completion, during a period of culpable delay, then liquidated damages will run up until that act of prevention. However, absent the clearest language, it should not matter whether an extension of time is sought, post or pre-the completion date and so, the liquidated damages regime should stay intact unless or until an action of prevention has occurred (notwithstanding possible issues as to the retrospective application of the extension of time).

Concurrent delay. Instances of concurrent delay, i.e., when there is "period of project overrun which is caused by two or more effective causes of delay which are of approximately equal causative potency," has been the subject of much legal debate over the years. The inherent conflicting interests of the owner and contractor in concurrent delay situations are illustrated in the accompanying diagram. The general thrust of the English approach on concurrent events is that the "contractor is entitled to an extension of time where delay is caused by matters falling within the clause notwithstanding the matter relied upon by the contractor is not the dominant cause of delay, provided only that it has at least equal 'causative potency' with all other matters causing delay."

The rationale for such an approach appears to be that by stipulating that a Relevant Event triggers an entitlement to an extension of time, the parties must have considered the possibility of other equal causes of delay operating at the same time, but have still viewed the right to an extension as paramount.

The approach seems sensible enough, but difficult questions can arise if the owner's acts or omissions had prevented the contractor from achieving the completion date (and there is no operative EOT mechanism for that act) but, nevertheless, that completion date would not have been achieved in any event because of concurrent delays caused by the contractor's own default. In this circumstance, the preventing act would not make an actual difference to the contractor missing the completion date. Should regard be had to the contractor's concurrent delay when the contractor itself is asserting an action of prevention?

Unfortunately, the English courts have not spoken with one voice on this issue. The need for the preventing act to cause actual delay to completion was emphasized by Justice Hamblen inAdyard Abu Dhabi v. SD Marine Service, and further doubts have been raised by Justice Coulson's comments in Jerram Falkus Construction v. Fenice Investments that the prevention principle does not apply in concurrent delay cases because the owner's act of prevention did not in fact delay completion.

This of course, does not sit neatly with other concurrent delay cases that appear to give paramount importance to the occurrence of the Relevant Event and its associated entitlement to an extension of time, notwithstanding the fact that the contractor would not have been able to achieve the necessary completion due to its own concurrent delay.

Practical tips

Clear and precise drafting of extension of time clauses can prevent or mitigate against the operation of the prevention principle. If seeking to contract out of the prevention principle, parties should be careful to avoid general language as "exceptional circumstances" or "any matters beyond the control of the builder" but to instead to identify specific acts of prevention that may give rise to an extension of time. This would inevitably involve FPSO owners recognizing the interactive nature of their construction project, as well as foreseeing and catering for possible delay events that may arise during the construction. Ultimately, the extension of time clause needs to be drafted to strike a balance between catering for a variety of situations including those highlighted in this article, while always ensuring that an EOT clause remain operable, to forestall arguments arising from the prevention principle.