Offshore staff
LUXEMBOURG – Total has awarded Subsea 7 an EPCI contract for the Zinia Phase 2 project in block 17, 150 km (93 mi) offshore Angola in water depths of 800-1,000 m (2,625-3,281 ft).
This involves the tieback of production from two reservoirs to the FPSOPazflor.
Subsea 7 will install around 36 km (22 mi) of flowlines and 21 km (13 mi) of umbilicals during 2020.
The company will perform project management and engineering in Paris and Luanda, with fabrication assigned to Sonamet’s yard in Lobito, Angola.