The two electricity generation permits are valid for 25 years from the time of grid connection (when the first kWh is delivered from the development).
Vesterhav Syd and Vesterhav Nord will have respective capacities of 170 MW and 180 MW.
Vesterhav Syd, 9-10 km offshore Hvide Sande and Søndervig, will comprise 20 8.4-MW Siemens Gamesa wind turbines, while Vesterhav Nord’s 21 turbines, from the same supplier, will be located 5.5-8.4 km offshore Harboøre.