DEME awarded T&I contracts for Yeu and Noirmoutier offshore wind farm

Feb. 10, 2023
The installation of the monopile foundations, substation jacket and topside are scheduled to start in the first half of 2024.

Offshore staff

BELGIUM  DEME has been awarded two transport and installation contracts for the foundations and the offshore substation for the Yeu and Noirmoutier islands’ offshore wind farm offshore France.

The combined contracts have a total value of more than EUR 300 million ($320.2 million).

DEME stated in its news release, "this is the second major offshore wind farm project in France following groundbreaking solutions and industry-first technology deployed at Saint-Nazaire."

DEME Offshore will execute the pre-piling works for the offshore substation jacket, and the transport and installation of the 2,700-tonne topside. The scope of work also includes the transport and installation of monopile foundations and transition pieces.

The wind farm is being developed by Éoliennes en Mer des Îles d’Yeu et de Noirmoutier (EMYN), a consortium including Ocean Winds (an ENGIE and EDPR joint venture), Sumitomo Corp., La Banque des Territoires and Vendée Energie.

Just like Saint-Nazaire, the wind farm is located in a very rocky area with challenging ocean conditions.

Therefore, the installation of the monopile foundations will again require DEME’s drilling technology, and some of the equipment, methods and tools deployed at Saint-Nazaire will be reused. This includes the giant 350-tonne Offshore Foundation Drill developed together with Herrenknecht and the so-called MODIGA. At 60 m high, the MODIGA encapsulates the drilling and installation operations, protecting them from the harsh marine conditions, which in turn, improves operational working time substantially, DEME said.

DEME’s Innovation offshore installation vessel will carry out the foundation installation. 

Similar techniques and vessels successfully deployed at the Saint-Nazaire wind farm will be used for the substation pre-piling works, which will be executed in the second half of 2023.

Allseas’ Pioneering Spirit vessel will be used to install the substation jacket and topside.

The installation of the monopile foundations, substation jacket and topside are scheduled to start in the first half of 2024.

Yves Chiffoleau, business unit director South Europe with DEME Offshore, said, “Many thought it was impossible to drill an entire wind farm into rock, but our expert project team successfully accomplished the project ahead of schedule,"

Paolo Cairo, president of EMYN, added, “This contract signature for the transport and installation of the monopile foundations and substation is an important step toward EMYN’s construction phase ensuring a proven technology for a challenging installation in safe conditions. As from 2025, the Yeu and Noirmoutier offshore wind farm will produce clean energy for almost 800,000 people."

02.10.2023