CADIZ, Spain –Dragados Offshore has reported the start of oil production from Pemex platform PB-KU-A2 in the Gulf of Mexico.
The platform Dragados did the engineering, procurement, fabrication, loading, connection, and commissioning of the facility. The installation consists of four connection bridges, two tripods, one substructure and one main structure.
The 8,400-metric ton (9,259-ton) main deck was installed in March and the remainder of the structures in April.