Production from the M07-A gas field in the Dutch North Sea remains shut in since Sept. 9, according to operator Cirrus Energy.
Offshore staff
CALGARY, Alberta -- Production from the M07-A gas field in the Dutch North Sea remains shut in since Sept. 9, according to operator Cirrus Energy.
This is due to unplanned repairs at the third party L09-FF processing platform. Cirrus was advised initially that the interruption would be relatively brief; however, the shutdown will likely now be prolonged to allow for further investigation and repair of the process equipment.
During August, production from the M07-A field averaged 30.5 MMcf/d of gas.