Offshore staff
STAVANGER, Norway — Equinor and the Wisting partners have decided to postpone the investment decision scheduled for December 2022. The maturation of the project continues, aiming for an investment decision by end of 2026.
Geir Tungesvik, Equinor’s executive vice president, Projects, Drilling & Procurement, said, “Equinor and partners have worked in close cooperation with the supply industry and developed a technically feasible and environmentally safe Wisting project for the Barents Sea. A development will generate substantial value for society and ripple effects in the north and nationally. In our updated investment estimate for the project, we see a cost increase due to increased global inflation and cost growth in the supply industry nationally and internationally. There is also uncertainty about the framework conditions for the project and execution capacity in the supplier market. Based on an overall assessment, we choose to postpone the investment decision."
Updated investment estimate for Wisting is NOK 104 billion (US$10.2 billion). The project has a positive net present value before and after tax after the cost increase.
Global inflation, and challenges in the energy markets because of the war in Ukraine, creates capacity challenges and bottlenecks among international and Norwegian suppliers. The lead time from the yards and from the equipment suppliers has increased.
“Many people have been working hard to realize Wisting, and the decision is demanding. However, in the current supplier market, postponing the investment decision to ensure an economically sound development and robustness in the execution phase of the project is the right decision. When the pressure in the supplier market subsides, the Wisting project will be possible to execute in a good way,” Tungesvik said.
Kjetil Hove, executive vice president for Exploration & Production Norway, added, “Equinor has been present in Northern Norway and in the Barents Sea for more than 40 years, and the industry has generated substantial value, activity, and jobs. We have a long-term perspective with the Castberg field coming on stream in 2024, we will continue to explore, and we will further develop the Barents Sea."
Equinor and partners will further mature the development concept, the power-from-shore solution and consider new supplier models for Wisting.
The Wisting partners are Equinor Energy AS (35%), AkerBP AS (35%), Petoro AS (20%) and INPEX Idemitsu Norge AS (10%).
Facts about Wisting:
- Wisting (PL 537) was discovered in 2013 by OMV
- Equinor is the operator in the development and operations phase
- The discovery is located in the Hoop area in the Barents Sea
- Wisting is located some 310 km north of Hammerfest
- Ocean depth between 390 m and 418 m
11.10.2022