ADMA-OPCO has awarded Hyundai Heavy Industries (HHI) a $1.84-billion contract for the second package of the Nasr full field development project, 131 km (81 mi) offshore Abu Dhabi.
HHI will perform engineering, procurement, construction, installation, and commissioning for the complex that will comprise a gas treatment platform, separation platform, and accommodation platform. It also will install 144 km (89 mi) of subsea power cables and 55 km (34 mi) of infield cables; modify an existing manifold tower and two wellhead towers on theNasr oil field; and implement work for power distribution facilities from DAS Island to the new complex.
All tasks are due to be completed during the first half of 2019. The new facilities will almost triple the field’s oil production capacity to 65,000 b/d.