Malaysian Berantai platform in place

Dec. 19, 2011
Petrofac says the jacket and topsides have been installed for the first wellhead platform for Petronas’ Berantai project off Malaysia.

Offshore staff

LONDON– Petrofac says the jacket and topsides have been installed for the first wellhead platform for Petronas’ Berantai project off Malaysia.

The drilling program has started on schedule, and the FPSO Berantai should sail to the field location around end-March 2012.

In block PM304 offshore peninsular Malaysia, gas lift facilities on the Cendor field should begin operating on year-end. Petrofac also expects the field development program for the West Desaru fault block to be approved early next year.